Specialty Repair
Industry: Water & Wastewater
Solution: Raw Sewage Piping
ID: SPR-7-00174
Project summary:
Inspectors at a water treatment plant found that six leveling troughs had severe corrosion causing water level issues. To repair the troughs, they were first completely drained and power washed before sand blasting could begin. Areas with pitting and through-wall failures were repaired using FRP Repair Putty, then the troughs were wrapped in a four-layer carbon fiber system on the inside and outside. A corrosive resistant topcoat was applied to finish the repair solution and provide the plant with a leak-free, 50-year life extension for these critical assets.
- Date of installation: 09/23
- Facility/Location: New York, NY
- End User: DEP
- Applicator: CTI
- Products used:
-
GF-300 BD
-
CF-500 BD
-
FRP 120 HT Adhesive
-
FRP Repair Putty
-
HP 300 Epoxy Grey
-
FRP 210 HT Saturant