Composite Pipe Repair
Industry: Power Generation - Fossil Fuel
Solution: Coal Pipe Elbows
ID: CPR-1-00044
Project summary:
A coal-fired power plant had through-wall failures in its coal pipe elbows running into their main boiler. The pipes were repaired by installing an abrasion-resistant ceramic repair putty reinforced with a carbon fiber composite.
- Date of installation: 5/1/2018
- End user: Power Generation Facility
- Facility/Location: Colorado Springs, CO
- Applicator: Internal Maintenance Team
- Products used:
- CF-500 BD
- FRP Saturant 210 HT
- Ceramic Repair Putty
- HP-300 HT